One Solar Battery for Two Buildings: House and Garage
Quick Answer:
A single solar battery can serve a house and a second building, but only when three numbers line up: the size of the feeder between the buildings, the busbar and main breaker rating of the second panel, and the number of utility eters involved. Miss any one of them and the project stalls after the deposit.
The short version: a solar battery does not care how many buildings it feeds. The wiring does. A 60 amp feeder between a house and a garage caps how much power can travel in either direction. A 125 amp subpanel busbar with a 60 amp main leaves 90 amps of backfeed room under the 120% rule, but the feeder still caps the trip at 60 amps. Two separate utility meters usually end the idea of one grid-tied solar battery serving both buildings, however good the equipment is.
So the order of questions is fixed. How big is the feeder? How much busbar room does the second panel have? How many meters? Only then does capacity matter.
- The feeder has two ceilings. The subpanel busbar rule and the feeder's own ampacity, and the lower one always wins.
- The main panel gets a third calculation. A feeder backfeeding the house counts as a source there, and that is where most two-building projects fail.
- One meter is a wiring project; two meters is a legal project. The utility decides the second case before any equipment is ordered.
This guide works through each number with the arithmetic an electrician would use, compares one large solar battery against two smaller ones, covers garage, duplex, and ADU cases separately, and ends with what an inspector will ask for. If you are still deciding whether a single unit fits your load at all, the sizing logic in our guide on solar battery sizing covers the single-building case in more depth.
In this guide
- Why this is a feeder question
- The three numbers to read
- Load diversity
- What a feeder can carry back
- The 120% rule at the second panel
- One meter, two meters
- One 40 kWh or two 20 kWh
- Distance and voltage drop
- Garage and shop loads
- ADU loads and Title 24
- An unheated outbuilding
- Worked example
- Sizing two buildings
- What the inspector asks for
- Frequently asked questions
Why This Is a Feeder Question, Not a Battery Question
Most buyers focus on battery capacity and price. But when a solar battery needs to power two buildings, the real question is whether the electrical wiring can handle the current.
A solar battery stores energy, while an inverter converts it into 240V AC power for household use. This power must travel through electrical wiring to reach the appliances.
When everything is in the same building, the connection is usually simple. But when you need to power a detached garage, workshop, ADU, or second house, the system may need a feeder. A feeder is the wiring that connects the main electrical panel to a subpanel in another building.
The problem is that an existing feeder may not be large enough for the new system.
For example, a 60A feeder installed in a garage in 1998 may have been designed for lights, a garage door opener, an air compressor, or a welder. It may not have been designed to carry additional power from a solar battery back to the main house.
Electrical current can flow in either direction, but the feeder must be rated for the current it carries. If the wire is undersized or the protection is not suitable, it can overheat and create a safety risk.
That is why you should check the feeder capacity before choosing a solar battery. A battery is a product you can replace or upgrade. Replacing an existing feeder may require new wiring, trenching, permits, and professional installation.
Three Common Projects and Their Challenges
Most projects involving one solar battery and multiple buildings fall into three common situations:
-
Detached Garage or Workshop: The battery may be installed near the tools and equipment, while the main house is some distance away. The existing feeder may limit how much power can be shared.
-
Duplex or Family Property: Two homes may share the same property but have separate electrical meters. This can affect how power is distributed and what electrical connections are allowed.
-
Accessory Dwelling Unit (ADU): A small additional home is built behind an existing house. The main electrical panel and feeder may need to support the extra loads.
These projects share similar electrical concerns, including feeder capacity, wire size, current, and subpanel connections.
However, their electrical and legal requirements can be different. Local codes, utility rules, metering arrangements, and property regulations may determine whether the proposed system is allowed.
Before buying a solar battery for multiple buildings, check the existing feeder, electrical panel, and local installation requirements. The battery capacity is only one part of the project.
The Three Numbers to Read Before Anything Else
You can answer most of the feasibility question in twenty minutes with a notebook and a phone camera. Three labels matter.
The feeder breaker. In the main panel, find the breaker feeding the other building. It might be labeled garage sub, shop, ADU, or just sub. Its number, 50, 60, 100, or 125, is the first hard limit. Nothing downstream can carry more continuous current than that breaker allows, in either direction.
The second panel's busbar and main. Open the subpanel door and photograph the sticker. You need the busbar rating, often 100, 125, or 200 amps, and the main breaker rating, which in a subpanel is usually the feeder breaker. Those two numbers feed the 120% arithmetic later.
The meter count. Walk to the meter base. One meter or two? One meter feeding both buildings is the clean case for a shared solar battery. Two meters on two accounts is the case that usually ends with two separate systems, because a grid-tied solar battery behind one meter cannot legally serve loads on another account without the utility's involvement.
Photograph the feeder conductors while you are out there, if the jacket label is legible. Aluminum 6 AWG and copper 6 AWG are not interchangeable at the same amperage, and old feeders are sometimes smaller than the breaker protecting them, which is its own problem to fix before adding anything.
If the subpanel has no main breaker, treat the feeder breaker as the main for the arithmetic. That is how the current path works, and it is what an inspector will assume when reading your one-line diagram.
Load Diversity: House Peak Plus Shop Peak Is Not the Sum
The instinct is to add everything. House peaks at 6 kW, shop peaks at 3 kW, so buy a 9 kW inverter. That number is too big, and buying to it is how a project ends up needing a service upgrade it never needed.
Two buildings almost never peak in the same minute. The house peaks in the late afternoon when air conditioning, a dryer, and an oven overlap. The shop peaks on a Saturday morning when a compressor kicks on while a welder runs. A solar battery serving both should be sized to the combined load with a diversity factor, not to the arithmetic sum.
| Building | Daily energy (kWh) | Peak demand (kW) | Notes |
|---|---|---|---|
| Main house | 12 | 6.0 | AC, dryer, oven overlap on summer afternoons |
| Detached shop | 4 | 3.0 | Compressor and welder, intermittent |
| ADU | 6 | 3.5 | Mini-split, heat pump water heater |
| Duplex, each unit | 10 | 5.0 | Two kitchens, two AC units |
A working planning assumption is to take the larger building's peak at full value and the second building's peak at 40 to 60 percent. This is engineering judgment, not a code requirement, and it belongs in design notes rather than a permit application. With the numbers above, combined peak is 6.0 + 0.5 × 3.0 = 7.5 kW, not 9.0 kW.
That difference matters at the breaker. A 9 kW inverter needs a 50 amp breaker after the 125 percent continuous factor. A 7.5 kW inverter needs 40 amps. On a 60 amp feeder, 40 amps leaves room and 50 amps does not.
Diversity is also the argument against oversized batteries. A shop that draws 4 kWh on a busy day does not need 20 kWh reserved for it. It needs the house covered plus a margin for the tools that run during an outage. The energy number and the power number are separate decisions, and mixing them is the most common sizing error in two-building projects. A solar battery is chosen for energy; an inverter is chosen for power.
Where diversity is not available: an outage with a medical device, a well pump cycling on its own schedule, or a shop running a continuous process. Size to the sum and accept the larger inverter, or split the system so each building has its own solar battery.
What a 60A, 100A, or 125A Feeder Can Carry Back
A feeder has two ceilings, and the lower one wins. The first is the busbar allowance at the subpanel, computed with the 120% rule. The second is the feeder's own ampacity, protected by the breaker at the main panel.
The counterintuitive result: on the same subpanel busbar, a smaller feeder can support a larger inverter than a larger feeder, because the subpanel main is smaller and the busbar rule gives back more room.
| Feeder | Subpanel main | Busbar allowance (125A bus) | Feeder ceiling | Effective limit | Largest inverter |
|---|---|---|---|---|---|
| 60A | 60A | 150 − 60 = 90A | 60A | 60A | 11.5 kW |
| 100A | 100A | 150 − 100 = 50A | 100A | 50A | 9.6 kW |
| 125A | 125A | 150 − 125 = 25A | 125A | 25A | 4.8 kW |
| 200A | 200A | 240 − 200 = 40A | 200A | 40A | 7.7 kW |
Read the 60A row carefully. The busbar arithmetic says 90 amps are available, and the wire says 60. The wire wins. But 60 amps of backfeed is already 11.5 kW of inverter, more than most garages will ever need.
Read the 125A row too. A bigger feeder with a bigger main squeezes the allowance to 25 amps, and the result is a smaller maximum inverter than the 60A feeder supports. That is not a reason to install a small feeder. It is a reason to check the subpanel busbar before assuming a bigger feeder means more capacity.
The practical takeaway: for a detached shop with a 60A feeder and a 125A subpanel, roughly 10 to 11 kW of inverter is the ceiling and an 8 kW unit is the comfortable choice. For an ADU on a 100A feeder with a 125A subpanel, 9.6 kW is the ceiling. For a house with a 200A service and a 200A busbar, the ceiling is 7.7 kW.
One limit is easy to forget: the feeder serves loads as well as backfeed. If the garage draws 25 amps while a solar battery pushes 40 amps toward the house, the feeder is carrying 65 amps in opposite directions at once, which it cannot do. In practice the battery discharges into garage loads first, and only the surplus travels, but the design should assume the worst case.
The 120% Rule Follows You Into the Second Panel
The busbar rule in NEC 705.12(B) does not stop at the main service. Where a power source feeds a panelboard through a breaker at the opposite end of the busbar from the main, the sum of the main and the backfed breaker may not exceed 120 percent of the busbar rating. A subpanel is a panelboard. The rule applies.
Available backfeed = (busbar rating × 1.2) − subpanel main
| Subpanel busbar | Subpanel main | Available backfeed | Battery breaker that fits | Verdict |
|---|---|---|---|---|
| 100A | 60A | 60A | 50A (9.6 kW) | Passes |
| 125A | 100A | 50A | 50A (9.6 kW) | Passes at the limit |
| 125A | 125A | 25A | 20A (3.8 kW) | Small systems only |
| 200A | 150A | 90A | 80A (15.4 kW) | Comfortable |
| 200A | 200A | 40A | 40A (7.7 kW) | Common ceiling |
Two placements matter here, and inspectors ask about both. The backfed breaker must sit at the opposite end of the busbar from the main, which in a small subpanel often means moving existing breakers to make physical room. The conductors from the inverter to that breaker must be sized for the breaker, not the inverter's nameplate kW.
Where this gets interesting is a solar battery in the garage feeding the house. The inverter's output lands on the garage subpanel, and from there it travels back through the feeder to the main panel. The subpanel passes the 120% test, the feeder passes its ampacity test, and the main panel then has to pass its own 120% test with the feeder counted as a source. Three panels, three calculations, one project.
That third calculation is where a two-building design usually fails quietly. A 60A feeder backfeeding the main panel counts against the main busbar allowance exactly like a solar breaker would. On a 200A busbar with a 200A main, the allowance is 40 amps, and a 60A feeder does not fit. The fix is at the main panel, not the garage: derate the main, move to a critical-load subpanel, or accept a smaller inverter.
One Meter, Two Meters: What Actually Decides It
The electrical arithmetic can pass and the project can still be impossible, because the meter decides who is allowed to share.
One meter, one account, two buildings. This is the clean case. A solar battery sits behind one service, the utility sees one interconnection, and the feeder is an internal wiring matter. A grid-tied solar battery can serve both buildings as long as the panels and feeders pass their calculations. Most detached garage and ADU projects on an existing service fall here.
Two meters, two accounts, one property. This is the hard case. A solar battery on account A cannot push power to loads on account B without the utility's agreement, because that is a transfer of metered energy between accounts. Utilities generally prohibit it, and the reason is not bureaucratic: the second meter's service equipment and the first meter's source were never designed as one system. The workable options are consolidating the meters into one account, keeping the solar battery off-grid and isolated from both services, or installing two separate systems.
Two meters, two owners. Worse again. Backfeeding a neighbor's service crosses a property line and creates a billing relationship most tariffs do not contemplate. Internal submetering exists, but it is a landlord-tenant arrangement, not a substitute for utility approval.
What to ask the utility, in writing, before buying anything:
- Does the property have one service or two?
- If two, can they be consolidated, and what does that cost?
- Is a parallel-connected solar battery allowed on this service, and what is the application?
- Is a visible, lockable disconnect required, and where must it be mounted?
- Does the utility require a relay or a specific inverter listing at this size?
The answers vary by state and utility, which is why no article can tell you the answer for your address. The Department of Energy's overview of solar and resilience explains the islanding behavior a grid-tied system must have, and that behavior is what the utility is protecting when it asks these questions.
One practical note for family compounds: the cheapest legal configuration is often one meter, one solar battery, and a feeder to the second dwelling, with the second dwelling's loads on a subpanel. The second dwelling loses separate billing, which is a family decision, not an electrical one.
One 40 kWh or Two 20 kWh: The Real Trade-Off
Once the feeder and panel pass, the next decision is shape: one large solar battery at one building, or two smaller ones, one per building.
The case for one large unit is simplicity. One inverter, one set of battery cables, one interconnection application, one place to maintain. The case for two units is independence: if one building's inverter fails, the other keeps running, each unit sits close to its loads, and the feeder is no longer in the critical path.
| Option | Battery list price (observed) | Inverter | Single point of failure | Wiring complexity | Expansion |
|---|---|---|---|---|---|
| 1 × 40 kWh + one 10 kW inverter | $2,418–$4,689 | One unit | Total loss if the inverter fails | Lowest | Second unit at the same bus |
| 2 × 20 kWh + two 8 kW inverters | $2,383 each; $4,766 for two | Two units | Partial loss only | Highest: two interconnections | Third unit on either side |
| 1 × 30 kWh + one 12 kW inverter | Mid-range | One unit | Total loss | Low | Room for one more unit |
The prices are what the product pages listed when this was written, and they move. Treat them as a shape, not a quote: two 20 kWh units cost roughly the same as one 40 kWh unit before you add the second inverter, the second set of cables, the second disconnect, and the labor to wire it.
Capacity is where the comparison gets honest. A 40 kWh unit at 90 percent usable depth gives about 36 kWh. Two 20 kWh units give the same 36 kWh, split across two boxes, and each box can only deliver what its own inverter can push. If the house needs 30 kWh over two days and the shop needs 6, one 40 kWh solar battery with a 10 kW inverter serves both. Two 20 kWh units with 8 kW inverters also serve both, and they cost more to install.
The reverse case is just as real. If the buildings sit 200 feet apart and the feeder is 60 amps, one solar battery in the garage forces all house power through that feeder. Two units, one at each building, keep the feeder for normal loads and remove the backfeed constraint entirely. Distance is the variable that most often flips the recommendation.
Battery-to-battery parallelism is the third option, and it is worth understanding before dismissing it. Units wired in parallel share the load and can be expanded one box at a time; the trade-offs are balancing, cabling, and a single BMS conversation instead of two. Our comparison of modular battery vs single unit covers the architectural difference, and the wiring side is in Parallel 48V LiFePO4 Batteries.
In product terms, the 40 kWh case is one box with a large BMS and one set of terminals: the 40kWh LiFePO4 battery for home energy storage is built for exactly this role, one solar battery serving a whole property through one inverter. The two-unit case is better served by the Moveable 51.2V 400Ah LiFePO4 Battery 20kWh, which can be placed in each building without a shared DC bus.
A rule of thumb that holds up in practice: if the buildings are within 50 feet and share a feeder of 100 amps or more, one large solar battery is usually simpler and cheaper. If they are more than 100 feet apart, or on separate meters, or if losing one inverter would take down a building that matters, two units is the better answer even at a higher sticker price.
Distance, Trench, and Voltage Drop
Distance affects two things: the voltage the loads actually see, and the cost of getting conductors between the buildings. Voltage drop is computed with the round-trip resistance of the conductors:
VD = 2 × length × current × resistance per foot
Using copper at 75°C, approximate resistance is 0.491 ohms per 1,000 feet for 6 AWG, 0.308 for 4 AWG, and 0.194 for 2 AWG. The examples below use 6 AWG, a common feeder size for a 60 amp run.
| Distance | Current | Conductor | Voltage drop | Percent of 240V |
|---|---|---|---|---|
| 50 ft | 24A | 6 AWG Cu | 1.2V | 0.5% |
| 100 ft | 24A | 6 AWG Cu | 2.4V | 1.0% |
| 150 ft | 24A | 6 AWG Cu | 3.5V | 1.5% |
| 100 ft | 50A | 6 AWG Cu | 4.9V | 2.0% |
| 150 ft | 50A | 6 AWG Cu | 7.4V | 3.1% |
Three percent is the usual design limit for a feeder, so the 150 foot run at 50 amps is already at the edge. These numbers are illustrative: an electrician will use the actual conductor, the actual terminations, and the local amendment, and will likely step up to 4 AWG for a long run at high current.
What distance changes about the design:
- Where the solar battery goes. Putting it near the loads keeps the inverter's output on a short run and leaves the long feeder for normal load current. A solar battery at the far end of a 150 foot feeder spends its life pushing current through the weakest link.
- Trench cost. A buried feeder needs a trench, conduit, and often a permit and inspection before backfill. That cost does not shrink when the battery gets smaller, which is one more argument for deciding the layout before the equipment.
- Temperature and access. An outbuilding may be unheated in winter and inaccessible in a storm.
For a shop 100 feet from the house, the practical answer is usually a solar battery at the shop with the shop on its own subpanel, and a feeder carrying only the shop's normal load. That removes the backfeed constraint at the main panel and simplifies the interconnection.
Garage and Shop Loads: 240V Tools Change the Number
A garage is not a house with fewer appliances. It is a building with motors that start hard.
A compressor drawing 15 amps running can pull 45 to 60 amps for a second or two at startup. A welder behaves like a resistive load with a step change. A table saw has a belt and a blade to accelerate. The inverter has to survive those moments, and a solar battery sized for daily energy will trip on a motor it was never told about.
| Tool | Running load | Startup multiple | Peak to plan for | Inverter to plan for |
|---|---|---|---|---|
| 3 HP air compressor, 240V | ~15A (3.6 kW) | 3× | ~45A (10.8 kW) | 12 kW |
| 30A welder, 240V | ~24A (5.8 kW) | 1.5× | ~36A (8.6 kW) | 10 kW |
| 1.5 HP table saw, 240V | ~8A (1.9 kW) | 2.5× | ~20A (4.8 kW) | 6 kW |
| 2-ton mini-split | ~10A (2.5 kW) | 1.3× | ~13A (3.2 kW) | 4 kW |
| EV charger, 32A continuous | 32A (7.7 kW) | 1× | 32A | 10 kW |
This is why the inverter decision comes before the battery decision in a shop. A 40 kWh solar battery with a 6 kW inverter cannot start a 3 HP compressor, however much energy sits in the cells. A 20 kWh battery with a 12 kW inverter can.
Three moves reduce the peak instead of buying for it. A soft starter spreads inrush over a second or two and can cut the peak by half. Staggered loads mean not running the compressor, the welder, and the saw at once during an outage. A dedicated shop circuit on the critical panel keeps the tools backed up and leaves the welder on the grid side if it is not needed.
For an EV charger, the honest answer is that an outage is not the time to charge a car. A 32 amp continuous load flattens a 40 kWh solar battery in about five hours with nothing else running. Most designs leave the charger off the backed-up panel.
The tool list also sets the feeder size. A shop with a 3 HP compressor and a 30A welder is a 60 amp feeder building, not a 30 amp one, and that number goes into the arithmetic above.
ADU: Heat, Hot Water, and the Title 24 Question
An ADU is a small dwelling with a full set of house loads compressed into 400 to 1,200 square feet. That makes it a harder battery customer than its size suggests.
| ADU load | Typical draw | Daily energy | Notes |
|---|---|---|---|
| Mini-split heat pump | 2.5 kW | 6–12 kWh | Heating dominates in cold climates |
| Heat pump water heater | 0.6 kW avg | 3–5 kWh | Higher recovery draw after showers |
| Induction cooktop | 3.0 kW peak | 1–2 kWh | Short, high peaks |
| Washer and dryer | 2.0 kW | 2–3 kWh | Heat pump dryers cut this in half |
| Lighting and plug loads | 0.3 kW | 2–3 kWh |
A 600 square foot ADU with a mini-split and a heat pump water heater lands around 12 to 20 kWh per day in a cold month, more than many owners expect. A 20 kWh solar battery covers roughly one day of normal use, or two days of essentials. A 5 kWh wall unit covers lights and a refrigerator and nothing else.
The California question comes up in almost every ADU thread, and it is a policy question, not an electrical one. New construction ADUs in California generally have to include solar, with limited exceptions, and the requirement is satisfied through the permit process. Whether an ADU needs its own array or can be covered by the main house's existing system depends on the local jurisdiction and the size of the existing array. The California Energy Commission publishes the ADU energy code FAQs, and that document, not a blog, is the reference an ADU builder should read.
What this means for a shared solar battery:
- If the ADU has its own array and inverter, it is a standalone system and the two-building question disappears. Size it like a small house.
- If the ADU shares the main house's solar, one solar battery can serve both through a feeder or subpanel, subject to the arithmetic above.
- If the ADU is on a separate meter, it is the two-meter case, and the utility decides.
The most common configuration is a shared meter, a 100 amp feeder to the ADU, and a 125 amp subpanel in the ADU. That subpanel allows 50 amps of backfeed under the 120% rule with a 100 amp main, which is 9.6 kW, more than the ADU will ever need. Putting the solar battery in the ADU and backfeeding the house is possible, but it then has to pass the main panel's own 120% test, and that test is usually the binding constraint.
A smaller unit placed in the ADU, like the 5KWH wall mounted LiFePO4 battery, is often the right call for a single small dwelling, while the main house keeps its own system. Two systems, two smaller inverters, no shared feeder problem.
An Unheated Outbuilding in February
A solar battery in a garage or shop lives in a harder environment than a house battery, and winter is where that shows up.
Lithium iron phosphate cells do not accept charge below freezing. The BMS blocks charging to protect the cells, which means a solar battery in a 25°F garage will discharge but will not recharge until it warms up. In a multi-day outage in February, that is the difference between a system that recovers and one that does not.
What works, in order of preference:
- Put the solar battery inside the conditioned space. An attached garage kept above freezing is fine. A detached shop in Minnesota is not.
- Use a unit with a heater. Some wall and floor units include internal heating pads that keep cells above the charging limit and draw a little power to do it. Ask for the operating temperature range in the datasheet, not the marketing page.
- Insulate the enclosure. A dedicated cabinet slows the temperature drop but does not solve a week of single digits.
- Accept discharge-only in cold snaps. If the design goal is summer storm season, a shop solar battery that cannot recharge in January may be acceptable. If the goal is winter ice storms, it is not.
Placement inside the building has its own constraints. NFPA 855 and local amendments govern clearance, separation from combustibles, and in some jurisdictions the maximum energy per room. The NFPA energy storage pages list the standards involved, including Article 706 of the National Electrical Code and NFPA 855 itself, and the local fire code is the version that applies on your street.
Two site questions decide where the solar battery goes: is the garage attached or detached, and does it flood? An attached garage shares a wall with the house and stays warmer. A detached garage on a slab in a low spot is the worst case for both temperature and water. The placement logic is covered in the guide on indoor vs outdoor installation, and it applies to outbuildings as well.
Worked Example: A Shop on a 60A Feeder
This example is a parametric scenario built to show the arithmetic, not a record of a specific customer's project. The numbers are typical of a 1990s subdivision and a detached shop.
The setup. Main house: 200 amp service, 200 amp busbar, 12 kWh per day, 6 kW peak. Detached shop: 60 amp feeder, 125 amp subpanel busbar, 60 amp main, 4 kWh per day, 3 kW peak when the compressor and welder overlap.
Step 1, combined peak. 6.0 kW + 0.5 × 3.0 kW = 7.5 kW.
Step 2, inverter. 7.5 kW ÷ 0.8 = 9.4 kW, rounded to a standard 8 or 10 kW inverter. Choose 8 kW to keep the breaker at 45 amps and leave feeder margin.
Step 3, breaker. 8 kW × 1,000 ÷ 240 = 33.3A, × 1.25 = 41.7A, next standard size 45A.
Step 4, subpanel check. 125A busbar × 1.2 = 150A, minus 60A main = 90A available. 45A fits with 45A to spare.
Step 5, feeder check. The 60A feeder caps backfeed at 60A. 45A fits.
Step 6, main panel check. The feeder backfeeds the main panel, so it counts as a source there. 200A busbar × 1.2 = 240A, minus 200A main = 40A available. A 45A backfeed does not fit, and the project fails at the main panel, not at the shop.
Step 7, capacity. Two days of combined load: 16 kWh × 2 = 32 kWh ÷ 0.9 usable depth = 35.6 kWh, plus 10 percent reserve = 39.1 kWh. One 40 kWh solar battery covers it; two 20 kWh units provide 40 kWh nominal and 36 kWh usable, which lands 3 kWh short of the reserve.
The fix. The main panel is the binding constraint, and there are three ways out. Derate the main from 200 to 175 amps if the measured peak allows it, which raises the allowance to 65 amps and lets the 45A backfeed in. Move the house's backed-up circuits to a critical-load subpanel and leave the feeder on the grid side. Or accept an inverter small enough that its backfeed fits under 40 amps, about 7.7 kW.
This scenario is why the three numbers matter. The shop passed, the feeder passed, and the main panel failed. A designer who checks only the second building would have ordered equipment and discovered the problem at the permit desk.
Sizing Two Buildings in One Pass
Sizing is two questions wearing one coat: how much energy for how many days, and how much power at the worst minute.
| Combined daily use | 24 hours | 48 hours | 72 hours | Sensible configuration |
|---|---|---|---|---|
| 10 kWh (8 + 2) | 11 kWh | 22 kWh | 33 kWh | 30 kWh single, or 16 + 16 |
| 16 kWh (12 + 4) | 18 kWh | 36 kWh | 53 kWh | 40 kWh single; two units beyond 48 hours |
| 26 kWh (20 + 6) | 29 kWh | 58 kWh | 87 kWh | Two 30 kWh, or 40 + 40 |
The energy column assumes 90 percent usable depth and no reserve; add another 10 percent if you want the buffer used in the worked example. The power side is separate: the inverter has to cover the combined peak with the diversity factor and the largest motor's startup, which is why a 40 kWh solar battery with a small inverter is a common mistake.
Two-building battery calculator
Enter the daily energy for each building, the peak for each building, how much the peaks overlap, and the outage length. The calculator returns the battery capacity, the number of units, the inverter size, and the breaker and feeder minimum.
Results appear here after you run the calculation.
Planning tool only. Final sizing, breaker selection, feeder design, and interconnection approval rest with a licensed electrician, the utility, and the authority having jurisdiction.
For a property in the middle row, a 30 kWh unit is the natural single-box answer, and it is the size our 30kwh moveable LiFePO4 lithium solar battery is built for. For a lighter property, a 16 kWh unit covers a house plus a small shop for 24 hours with margin, and the 16kwh solar battery for residential energy storage is the matching product.
The order of decisions that avoids rework:
- Measure the feeder and both panels.
- Confirm the meter count and call the utility.
- Compute the combined peak with diversity.
- Choose the inverter from the peak, not from the battery.
- Size the solar battery from daily energy, days, and usable depth.
- Pick one unit or two based on distance and independence, not price alone.
- Re-check the main panel with the backfeed counted as a source.
Steps 1 and 7 are the ones buyers skip, and they decide whether the equipment can be connected at all.
What the Inspector Asks For
A two-building install has more paperwork than a single-building one, because the inspector has to verify a feeder, two panels, and an interconnection.
| Item | Why it is requested | Where it comes from |
|---|---|---|
| Photos of both panel labels | Confirms both 120% calculations | Your phone, before the covers go back on |
| One-line diagram covering both buildings | Shows sources, feeders, subpanels, disconnects | Your designer or installer |
| Feeder conductor size and length | Supports ampacity and voltage drop | The electrician's as-built notes |
| Inverter datasheet with continuous output | Ties the breaker to a listed number | Manufacturer documentation |
| UL 9540 listing for the storage system | Confirms the unit is a listed ESS | UL Solutions or the manufacturer certificate |
| Utility interconnection approval | Required before any parallel source is energized | The utility, in writing |
| PCS listing and settings, if used | Proves a current limit under 705.13 | The PCS manufacturer |
The UL listing deserves a note. A residential solar battery system is typically listed to UL 9540 as a system, with cells and inverter evaluated under their own standards. The UL residential ESS program page explains what that listing covers. A certificate naming only the cells is not a system listing, and an inspector who knows the difference will ask for the system certificate.
Two inspection-day failures show up repeatedly. The first is a feeder breaker larger than the feeder conductors, usually because someone upgraded the breaker years ago without changing the wire. The second is a missing disconnect at the second building, which some utilities require for line worker safety. Neither is a solar battery problem, and both stop the sign-off.
Frequently Asked Questions
Can one solar battery power two houses?
Technically yes, if the solar battery and inverter are large enough for the combined load, typically 30 to 50 kWh with a matching inverter. Legally, the answer depends on the meters. Two houses on two utility accounts cannot share one grid-tied solar battery without the utility's agreement, because that transfers metered energy between accounts. Two dwellings on one meter, connected by a feeder, is the configuration that usually works. A compound with two separate services is usually better served by two systems.
Can I put a solar battery in a detached garage?
Yes, and it is a common placement for a shop, subject to three conditions. The garage subpanel has to pass the 120% rule with the inverter's breaker, the feeder has to carry the backfeed, and the space has to satisfy NFPA 855 and the local fire code for clearance and separation. Temperature matters too: an unheated garage in a cold climate will block charging in winter unless the unit has internal heating.
Do ADUs require solar panels in California?
New construction ADUs generally do, with limited exceptions, and the requirement is handled through the building permit. Whether the ADU needs its own array or can be covered by an existing array on the main house depends on the local jurisdiction and the size of the existing system. The California Energy Commission's ADU energy code FAQ is the document to check, and a local ADU builder will know current practice in your city.
How many solar panels and batteries to run a 2,000 sq ft house?
A 2,000 square foot house typically uses 25 to 35 kWh per day in a mixed climate, which points to a 5 to 7 kW array and a 20 to 30 kWh solar battery for one day of backup, or 40 kWh for two days. Panel count follows array size at roughly 400 watts per module, so 13 to 18 modules. The battery number should be set by the loads you want to keep running, not by square footage.
What happens if the two buildings have separate meters?
A solar battery behind one meter cannot legally serve loads behind another without the utility's agreement, and most tariffs prohibit it. The options are consolidating the two services into one account, keeping the solar battery isolated from both services in an off-grid configuration, or installing two separate systems. Consolidation is usually the cheapest of the three, and it is a utility decision, not an electrical one.
Can I add a second battery later instead of buying one big one?
Yes, and it is often the better plan. Parallel-capable units can be added one at a time, which spreads the cost and lets you learn your real outage load before buying the second box. Two conditions apply: the first unit's inverter has to work alongside a second unit, and the panel has to have room for the additional breaker. Buying the larger panel now and the second solar battery later is a common and sensible sequence.
How long will a 30 kWh battery last across two buildings?
At a combined 16 kWh per day, a 30 kWh solar battery with 90 percent usable depth delivers about 27 kWh, roughly 40 hours of normal use or two days of essentials. At 26 kWh per day across a larger house and a shop, the same solar battery lasts about 25 hours. The number that matters is the daily energy of the loads you back up, not total house consumption.
Does a battery in an unheated garage work in winter?
It discharges fine and it will not recharge below freezing, because the BMS blocks charging to protect the cells. In a short outage that is tolerable. In a multi-day winter event it is a design flaw. Solutions are an internal heater, an insulated enclosure, or moving the solar battery into conditioned space. Check the datasheet's charging temperature range before choosing a location.
Bottom Line: Five Checks Before You Buy the Second Battery
- Measure the feeder before you compare batteries. The breaker feeding the second building sets the ceiling for everything downstream, in both directions.
- Run the 120% arithmetic at both panels. The second panel and the main panel each get their own calculation, and the main panel is usually the one that fails.
- Count the meters and call the utility. One meter is a wiring project. Two meters is a legal project, decided before any equipment is ordered.
- Size the inverter to the peak, the solar battery to the days. A large battery behind a small inverter cannot start a compressor, and a large inverter behind a tight panel cannot be connected.
- Choose one unit or two by distance and independence. Under 50 feet with a 100 amp feeder, one unit is simpler. Over 100 feet, or separate meters, two units win even at a higher price.
A solar battery that serves two buildings is not a bigger version of a single-building system. It is a feeder design with a battery attached. Get the feeder, the panels, and the meters right, and the storage becomes the easy part. Get them wrong, and no amount of capacity will fix it.
Planning a solar battery for a house plus a garage, duplex, or ADU? Send a photo of both panel labels, the feeder breaker size, and the meter count. We will run the same arithmetic against the buildings you actually have.